The government is likely to extend the deadline for the PM-KUSUM scheme once again, as two major components of the initiative have failed to achieve even 50 per cent of their targets, an official source said. Launched in 2019, the Pradhan Mantri Kisan Urja Suraksha evam Utthaan Mahabhiyan (PM-KUSUM) aimed to add a solar capacity of 30,800 MW by 2022, with a total central financial support of Rs 34,422 crore, including service charges for implementing agencies.

Later, the Centre extended the PM-KUSUM scheme till March 2026, as its implementation was significantly affected due to the pandemic, and also revised upwards the target to 34,800 MW. According to an official source, the deadline for the implementation of PM KUSUM is likely to be extended further to ensure the envisaged targets are achieved. This will be the second extension to the scheme.
As per official data, none of the components of the ambitious scheme have achieved 100 per cent target. Although component B of the scheme - which ends March 2026 -- has been able to meet 71 per cent of the target as on September 9, component A has registered a growth of just 6.5 per cent, and Component C (IPS) and Component C (FLS) -- 16.5 per cent and 25.5 per cent, respectively.
According to the Ministry of New and Renewable Energy (MNRE), Component A is for the installation of 10,000 MW of solar capacity by installing small solar power plants, Component B is for the installation of 14 lakh off-grid standalone solar-powered agriculture pumps, and Component C is for the solarisation of 35 lakh grid-connected agriculture pumps. Under Component A, only 650.49 MW capacity has been installed.
States like Telangana, Tripura, Odisha, Gujarat, and Assam have reported nil installation.The installation was in single digit in Uttar Pradesh (1 MW), Tamil Nadu (3 MW), Maharashtra and Goa (4 MW), and Chhattisgarh (7 MW). As part of Component B, over 12.72 lakh off-grid solar pumps have been sanctioned, of which 9.03 lakh have been installed. Andaman and Nicobar, Puducherry and Telangana have reported nil installations as of September 2025.
More From GoodReturns

New PAN Card Rules From April 1, 2026: How To Apply For New PAN Card Via Protean, E-Filing Portal?

LPG Gas Cylinder Prices Hiked Again From April 1; 19 KG LPG Gets Costlier By Rs 218; 14.2 KG LPG Unchanged

Gold Rate in India Rises Over Rs 37,000/24K in Three Days; Will Jump in Gold Price Today Continue on 31 March?

Gas Cylinder Booking Rules: 5 Things To Know For Your 14.2Kg, 19KG, 5KG, 10KG LPG Booking In April 2026

Gold Rate Today Continues Rally, 24K Jumps Over Rs 35000 in 2 Days; 22K & 18K Gold, Silver Prices in Delhi

Bank Holiday In April 2026: Banks To Be Closed For 14 Days; Good Friday, Baisakhi To Akshaya Tritiya

Gold Price Today Declines After 3-Day Surge; Check Latest 22K, 24K, 18K Gold & Silver Rates in Delhi on 2April

Gold Price Today, April 3: 22K, 24K Rates Jump Across Tanishq, Malabar, Kalyan & Joyalukkas & IBJA

5 New Shares On One Soon: Anil Agarwal's Vedanta Demerger To Take Place in April, Says Report

Fresh Drop in Gold Rate Today; Silver Stable: Latest 22K, 24K, 18K Gold & Silver Prices in Delhi on 30 March

Govt Approves PDS Kerosene Distribution in 21 States for 60 Days, Sets 5,000 L Storage Limit Amid LPG Crisis



Click it and Unblock the Notifications